Partners, contracts and who pays
EF&R is paid for in two different ways. Three contract agencies buy a defined service at its actual cost plus a 10% fee. Five partners fund whatever is left. Package 2 of the Board Q&A explains how overtime is split, what happens at year-end, and whether partners are carrying costs that belong to the contracts.
Issaquah, Sammamish, North Bend, FD 10, FD 38
Interlocal Agreement formula: 85% assessed valuation, 15% weighted call volume, applied station by station. It isn’t based on the cost of service.
- They fund
- The residual: what’s left after contract payments and all other revenue.
- Year-end
- No true-up in either direction.
- If overtime runs over
- Not automatically rebilled. It’s an EF&R variance handled through extra revenue, biennium capacity or a Board action.
Woodinville F&R, Mercer Island, FD 45 (Duvall)
Service agreements: actual personnel + allocated overtime + operations, plus a 10% administration fee. Operations, equipment and facility charges rise 3% a year.
- They fund
- The staffing and rank mix each one purchased.
- Year-end
- Personnel and overtime reconciled to actual by April 30 the following year.
- Not reconciled
- The 10% fee, which is set on budgeted costs.
How overtime gets paid
Overtime is budgeted as one agencywide pool and billed out by staffing share, not by where the overtime happened or by each agency’s past experience.
Budget the pool
2027: $8,183,874 of operations overtime plus pension, Medicare and PFML on those hours = $8,769,471.
Bill by staffing share
Each contract is billed its share of the 241 positions (232 on shifts + 9 uniformed day staff).
Reconcile in spring
By April 30, each contract’s personnel and overtime are trued up to actual, producing a bill or a credit.
The rest is EF&R’s
Anything left is an operating variance. It’s not passed back to partners automatically.
2027 overtime pool, $8.77M
Initial billing by suppression staffing share
“Will partners be overbilled from the outset?”
No, says staff. Initial billing just applies each contract’s staffing percentage to the adopted pool. Reconciliation then adjusts to actual costs. What’s left for partners is timing, not a permanent transfer of contract costs.
Budgeting overtime at its real cost ($6.42M in Suppression, instead of $3.26M) should also shrink the gap between what contracts are billed during the year and what they owe at reconciliation.
Small correction from Package 1: Woodinville’s 2027 allocation is $1,928,407 (not $1,928,556), and the three contracts total $3,820,575.
It swings both ways
The combined personnel-and-overtime true-up for each contract. Positive means the agency owed EF&R more than it was billed; negative means EF&R credited money back.
Net reconciliation by contract
Owed to EF&R (+) or credited back (−)
Mercer Island joined in 2024 and Fire District 45 in 2025. The results reflect actual payroll, vacancies, staffing changes and contract-specific credits. They don’t show which agency caused overtime.
“Count on this spring’s reimbursement to lower 2027 partner bills”
Staff recommends against it. In 2024 the contracts owed EF&R $725,005. A year later EF&R credited back $505,608. That’s a $1.2M swing in the direction nobody would have budgeted. If an assumed payment doesn’t come, the partner formula isn’t recalculated, and the gap has to come from other revenue, biennium capacity or a Board action.
Partner contributions are set before the reconciliation is known, so the operating fund carries a timing difference. A reconciliation is recognized only once its amount and direction are known. The 2027 revenue model includes contract payments that can be reasonably estimated, and no reconciliation payment.
Are partners subsidizing contract overhead?
The Board asked what share of the new support positions the contracts “necessitate,” and whether the 10% fee covers it. Staff’s answer: there’s no defensible way to split support work by funding source. The evidence doesn’t show partners subsidizing contracts.
The 12 are a Finance Director, a Finance Specialist, 2 facilities technicians, 2 administrative assistants, a mechanic, 3 assistant fire marshals, an HR specialist and a division chief. The contracts get no fee credit for them, and they work agencywide.
Records, payroll, finance, fleet, facilities and prevention are delivered for EF&R and the three contracts: four budgets and four state audits. Contract-funded staff support partners, and partner-funded staff support contracts. Comparing only the increase in the fee with the new positions’ cost leaves most of that picture out.
- Finance: 5 staff support nearly 300 employees, 4 budgets and 4 audits.
- Fleet: ~150 assets. The 42 response apparatus average 11.7 years old; 13 are 15+ years and tenders average 20.
- Public records: one executive assistant works full time plus nights and weekends on confidential requests. The combined load exceeds one full-time job.
Same formula, different increases
All three contracts use the same cost framework. Their increases differ because of what each one buys: rank mix, staffing changes and share of overtime. These use recurring total cost; the Board question’s percentages came from earlier schedules.
What moved: Mercer Island vs. FD 45
Change by component, 2026 → 2027
Overtime jumps for every contract because the overtime pool is now budgeted at real cost. Operations and M&O rise a fixed 3%.
Why FD 45’s personnel line is flat
| Position | 2026 | 2027 |
|---|
Converting two Captains to Lieutenants saves about $44,000. Dropping the Division Chief and Administrative Assistant saves about $430,000. Together they offset the 3.8% raise and much of the overtime increase. Daily emergency staffing didn’t change.
Why Mercer Island rises most: 4 of its 28 suppression positions (14.3%) are Battalion Chiefs, the most expensive rank, vs. 7.5% for Woodinville and none for FD 45. The same percentage raise produces more dollars. Two adjustments softened it: an Assistant Fire Marshal replaced a Fire Marshal-level charge, and the Care Coordinator moved into the levy-funded MIH program.
Contracts pay their share, and partners take the timing risk
Contract agencies pay what their agreements set: reconciled personnel and overtime, operations, and the fee, plus 12 agencywide support positions. That money reduces the partner requirement. What partners do carry is the uncertainty: they have no year-end true-up, and any agencywide overrun left after contract reconciliation becomes EF&R’s to manage.
- ✓Contracts are trued up to actual every spring, in both directions.
- ~The fee isn’t reconciled. It’s 10% of budgeted costs, whatever overtime turns out to be.
- !Don’t budget the true-up. It swung from +$725K to −$506K in one year.
- iNo cost-allocation method exists that would split support work by funding source. Building one would be a policy project of its own.